Bungalow Refurbishment 

This bungalow will be stripped back to its shell before the layout is remodelled. Initial works will involve the removal of asbestos and widening the driveway to improve access for trades during the project and for our client, once it is complete. The renovation will include the installation of various energy saving measures - an air source heat pump, solar panels and electric car charger -as well as underfloor heating, a new kitchen and bathrooms, and replacement doors and windows. Electrical and plumbing alterations, along with redecoration, will complete the refurbishment, leaving the home ready for our clients to move in. 
Existing Bungalow
Interior before strip out
Driveway Works
Internal strip out & remodelling
Strip out of sitting room
Flat Roof Replacement
Progress of Roofing Works
Flat roof completed & Doors & Windows being installed
Solar plans installed as well as air source heat pump
Air source heat pump installed
Structural Alterations Progressing
Plumbing & electrical first fix in progress
Doors, window & flooring fitted.  2nd Fix electrics & plumbing to start.
Bathrooms - sanitary ware fitted and tiling complete
Second fix plumbing & heating in progress, kitchen fitted and decoration started